EZH and EZHSO Series
11
Pilot Adjustment
For PRX Series pilots (Figure 13), loosen locknut
(key 2) and turn the adjusting screw into the spring
case to increase (or out of the spring case to
decrease) the downstream pressure. When the
required downstream pressure is maintained for
several minutes, tighten the locknut to lock the
adjusting screw in position.
PRX Series Pilot Restrictor and
Damper Screw Adjustment
Note
Recommended initial setting of the
restrictor screw is turned completely in
(clockwise) and then turned out 1 turn.
The damper screw initial setting is turned
completely out (counterclockwise).
The Type PRX/125 (upstream monitor
pilot in working monitor installations)
does not have a restrictor screw.
The Damper and Restrictor screws on the PRX Series
pilot control the regulator’s proportional band (droop)
and speed of response. For additional tuning follow the
steps outlined below, refer to Figure 13.
1. Start with the restrictor screw (R) 1 turn
counterclockwise from fully seated (turn restrictor
fully clockwise then 1 turn counterclockwise) and
the damper screw (D) fully counterclockwise.
2. Turn damper screw clockwise until desired
performance is achieved. This reduces the ow
path of the damper. If the damper becomes
fully seated (no longer able to turn clockwise)
and the desired performance has not been
achieved, return the damper screw to the fully
counterclockwise position.
!
WARNING
The damper screw should not be left in
the fully seated position, as it will lock
the regulator in last position which could
cause incorrect pressure regulation.
3. Turn the restrictor screw an additional turn
counterclockwise from fully seated. This increases
the ow path of the restrictor. If additional tuning
is required, repeat step 2. Follow this method until
desired performance is achieved.
Startup
For EZH Series
1. Make sure all block valves, vent valves and
control line valve(s) are closed.
2. Back out the pilot adjusting screw(s).
3. Slowly open the valves in the following order:
a. Inlet block valves
b. Pilot supply and control live valve(s), if used
4. Crack open the outlet block valve or bypass valve
to allow minimum ow.
For a single regulator (Figure 3), set the pilot to
the desired outlet (control) pressure according to the
Pilot Adjustment procedure.
For a wide-open downstream monitor installation
(Figure 5), adjust the upstream working pilot until
intermediate pressure is higher than the desired
setpoint of the monitor pilot. Adjust the downstream
monitoring pilot to the desired monitoring takeover
pressure. Reduce the upstream pilot to the normal
outlet pressure setting.
For a wide-open upstream monitor installation
(Figure 5), adjust the downstream working pilot to a
setpoint higher than the setpoint of the monitor pilot.
Adjust the upstream monitoring pilot to the desired
monitoring takeover pressure. Reduce the downstream
pilot to the normal outlet pressure setting.
For a working monitor installation (Figure 6),
adjust the setpoint of the upstream monitor pilot
Type PRX/125 to the desired maximum pressure.
Adjust the upstream working pilot Type PRX/120 to
the desired intermediate pressure setting. Adjust the
downstream pilot to a pressure setting slightly above
the upstream monitor pilot pressure setting. Adjust the
upstream monitor pilot Type PRX/125 to its desired
setpoint. Establish nal desired downstream pressure
by adjusting the downstream working regulator pilot.
5. After adjusting the PRX Series pilot(s) to the
desired pressure setting(s), slowly open the
downstream block valve wide open.
6. Close the bypass valve, if used.
For EZHSO Series
1. Make sure all block valves, vent valves and
control line valve(s) are closed.
2. Back out the pilot adjusting screw(s).
3. Introduce upstream pressure by slowly opening
inlet valve.
Zobrazit stránku 10