Reference Manual
00809-0200-4801, Rev CA
July 2010
2-17
Rosemount 3051S Series
NOTE
If using thread tape, be sure the thread tape does not strip when the manifold
assembly is started.
5. Wrench tighten manifold into process connection. (Note: Minimum torque
value is 425 in-lbs)
6. Count how many threads are still showing. (Note: Minimum engagement
is 3 revolutions)
7. Subtract the number of threads showing (after tightening) from the total
threads to calculate the revolutions engaged. Further tighten until a
minimum of 3 rotations is achieved.
8. For block and bleed manifold, verify the bleed screw is installed and
tightened. For two-valve manifold, verify the vent plug is installed and
tightened.
9. Leak-check assembly to maximum pressure range of transmitter.
Rosemount 304
Conventional Manifold
Installation Procedure
To install a 304 Conventional Manifold to a 3051S transmitter:
1. Align the Conventional Manifold with the transmitter flange. Use the four
manifold bolts for alignment.
2. Finger tighten the bolts, then tighten the bolts incrementally in a cross
pattern to final torque value. See “Flange Bolts” on page 2-5 for complete
bolt installation information and torque values. When fully tightened, the
bolts should extend through the top of the module housing plane of
flange web (i.e. bolt hole) but must not contact module housing.
3. If applicable, install flange adapters on the process end of the manifold
using the 1.75-in. flange bolts supplied with the transmitter.